Site A typical sewers for adoption pumping station (approximately twelve such schemes completed over the last four years).
Objective To undertake a full upgrade of existing pumping stations or installation of new build stations.
Solution We offered a complete M&E solution including the design, manufacture, supply, installation and commissioning of MCC, valves, pipework, pumps, level controls, flowmeter, telemetry and PID loop controls.
Notes All work was completed on time, working in liaison with civil contractors and including implementation of traffic control systems